- 12:18, 27 June 2024 Lennarz talk contribs uploaded File:Technical Note – How to Swap Out Omega CN76000 Series PID Controller.pdf
- 12:18, 27 June 2024 Lennarz talk contribs created page File:Technical Note – How to Swap Out Omega CN76000 Series PID Controller.pdf
- 12:14, 27 June 2024 Lennarz talk contribs created page IC PID controller (Created page with "File:DRAGON PID Settings.pdf")
- 12:13, 27 June 2024 Lennarz talk contribs uploaded File:DRAGON PID Settings.pdf
- 12:13, 27 June 2024 Lennarz talk contribs created page File:DRAGON PID Settings.pdf
- 11:35, 9 November 2023 Lennarz talk contribs created page IC windows (Created page with "There are right now 7 functional windows for the Dragon IC. All of them have been tested and there is a record of the pressure both on the ionization chamber and the other side of the window for each. NAME THICKNESS (micrometers) PRODUCT DATE TOP PRESSURE TESTED WINDOW A 1,5 13.07.2017 19 WINDOW B 1,5 08.2018 25 WINDOW C 0,9 08.07.2002 14 WINDOW D 0,9 17.07.2019 (new) 14 WINDOW E 0,7 18.07.2019 (new) 11 WINDOW F 0,5 (with wires) 16.06.2015 9 WINDOW...")
- 12:56, 22 September 2023 Lennarz talk contribs uploaded File:ICS2 MCP0.png
- 12:56, 22 September 2023 Lennarz talk contribs created page File:ICS2 MCP0.png
- 12:53, 22 September 2023 Lennarz talk contribs uploaded File:ICS2.png
- 12:53, 22 September 2023 Lennarz talk contribs created page File:ICS2.png
- 12:42, 22 September 2023 Lennarz talk contribs created page High Voltage - ISEG power supply (Created page with "As mentioned in the previous group meeting, the new MPOD crate has been installed. We have two new modules 1x 3kV and 1x 500V. Each are 16 channels. These can accommodate both polarities. Channels 0-7 are negative and 8-15 are positive. The controller module is CC24, which can interface with EPICS. These modules can be operated via the iseg software or the web interface. The host name for the control module is dragonhv02.triumf.ca and sits behind the TRIUMF firewal...")
- 10:12, 18 January 2022 Lennarz talk contribs created page TRIUMF collaborators (Created page with "*Ahmed Hussein *Alan Chen *Alison Laird *Annika Lennarz *Barry Davids *Chris Ruiz *Dave Hutcheon *Gavin Lotay *Greg Christian *Luis Wagner *Martin Alcorta *Matt Williams *Pete...")
- 09:39, 18 January 2022 Lennarz talk contribs created page MCP foils (Created page with "*New MCP foils can be ordered from Micromatter. [https://www.micromatter.com/ https://www.micromatter.com/]")
- 09:35, 18 January 2022 Lennarz talk contribs created page Lock up DRAGON (Created page with "Lock-up Procedure (Radio-active Beams) Overview Before radio-active beam can be delivered to DRAGON, fence gates must be closed and locked to prevent access within 1 metre o...")
- 09:34, 18 January 2022 Lennarz talk contribs created page Parts to be purchased (Created page with "*Chiller *Scopes *IV11 repair kit (purchased; has not arrived yet) *Pulser?")
- 11:12, 14 January 2022 Lennarz talk contribs created page Specifications (Created page with "[https://documents.triumf.ca/docushare/dsweb/Get/Document-153724 DRAGON Vacuum System Interlocks]")
- 13:50, 3 November 2021 Lennarz talk contribs created page DRAGON counting room and experimental area (Created page with "TRIUMF switchboard: 604-222-1047 *DRAGON experimental area: Ext. 7513 *DRAGON counting room: Ext. 7514")
- 13:49, 3 November 2021 Lennarz talk contribs created page DAQ (Created page with "TRIUMF switchboard: 604-222-1047 *Konstantin Olchanski: Ext. 6597")
- 13:47, 3 November 2021 Lennarz talk contribs created page DRAGON Facility Coordinator and Alternates (Created page with "TRIUMF switchboard: 604-222-1047 *Chris Ruiz: Ext. 7666 *Annika Lennarz: Ext. 6807 *Peter Machule: Ext. 7384")
- 13:46, 3 November 2021 Lennarz talk contribs created page Operations (Created page with "TRIUMF switchboard: 604-222-1047 *ISAC control room: Extension 7500 *Main cyclotron control room: Extension 7333")
- 13:30, 3 November 2021 Lennarz talk contribs created page Safety reports (Created page with "[https://documents.triumf.ca/docushare/dsweb/Get/Document-104594 DRAGON blanket safety report]")
- 12:46, 3 November 2021 Lennarz talk contribs created page Hardware (Created page with "{| class="wikitable" !colspan="11"|Hardware task list |- |'''Task''' |'''Type''' |'''Task Coordinator''' |'''Status''' |'''Action required''' |'''Date of status update''' |- |...")
- 12:37, 3 November 2021 Lennarz talk contribs created page EPICS (Created page with "{| class="wikitable" !colspan="11"|EPICS task list |- |'''Task''' |'''Type''' |'''E-fault number''' |'''Task Coordinator''' |'''Status''' |'''Date of status update''' |'''Dead...")
- 12:33, 3 November 2021 Lennarz talk contribs created page Repair/Fault task list (Created page with "* EPICS * Hardware * Computing")